Under the agreement between the two governments, Vietnam will buy 1,000 MW from Laos by 2020, while the figure would be 3,000 MW by 2025 and 5,000 by 2030.

 

{keywords}


The electricity volume to be imported from China will also increase from 2021. The import price will be more competitive than from Laos and lower than the average price of coal-fired plants (over 7 cent per kwh).

According to the Power and Renewable Energy Agency, Vietnam will lack 3.7 billion kwh by 2021 and 10 billion kwh by 2022.

The electricity shortage will be even more serious in 2013, about 15 billion kwh. However, the figure will decrease later to 7 billion and 3.5 billion kwh in 2024 and 2025, respectively.

The electricity volume to be imported from China will also increase from 2021. The import price will be more competitive than from Laos and lower than the average price of coal-fired plants (over 7 cent per kwh).

Vietnam still cannot mobilize electricity from wind and solar power plants. Many wind power plants have had to cut capacity because of the overloading of transmission lines.

Tran Dinh Long, deputy chair of the Vietnam Power Association, said it will take time to develop electricity generation units. The time needed for coal-fired and hydropower is three to five years.

However, Vietnam doesn’t have endless resources for hydraulic power. As for coal-fired thermal power, there are many problems related to supply and environmental pollution.

In principle, wind and solar power can develop more rapidly, especially solar, as the time for construction is short, from 6-7 months to one year.

Long said Vietnam has great potential to develop solar power, but the distribution of in is not equal. In some provinces, the potential is great, but the transmission network is weak.

Meanwhile, developing the network cannot be done overnight. In general, it takes several years to build a transmission line or a new power station. Though solar power plants have been built, they have had to run at limited capacity.

Responding to criticism that Vietnam has to buy electricity from other countries while its power plants cannot run at full capacity, Long said that importing electricity is normal practice because it transfers electricity from places with plentiful capacity to others with electricity shortages.

He said Vietnam can both import electricity and develop diverse electricity sources at the same time.

Kim Chi 

 

Korean firms to expand investment in electricity in Vietnam

Korean firms to expand investment in electricity in Vietnam

The Republic of Korea (RoK)’s Consulate General recently revealed the country’s businesses plan to invest more in Vietnam, especially in the manufacturing of electronic equipment and developing smart grid networks.  

Vietnam faces electricity shortage amid heat wave

Vietnam faces electricity shortage amid heat wave

Vietnam Electricity Group (EVN) could face difficulties in its electricity supply in the coming time due to the shortage of water, coal and gas for power production.