VietNamNet Bridge – The Ministry of Transport has asked the Prime Minister to invest in a section of the North-South Expressway from Ninh Binh Province to Thanh Hoa under a Public-Private Partnership (PPP).
The 140km Da Nang – Quang Ngai section of the North-South Expressway—Photo vov.vn |
Under the ministry’s proposal, the 63.3km Ninh Binh-Thanh Hoa Expressway will have four lanes and be completed by 2021.
Total investment is estimated at VND13.2 trillion (US$575 million), of which VND10 trillion ($437.2 million) will come from investors and the rest from the State budget.
The toll for the road is planned at VND1,500/km/ per car (during the 2021-2023 period) and will be increased slightly to VND1,700/km/per car (2024-2026).
The toll will reach VND3,400/km/per car from 2042-46, according to the Ministry of Transport.
Based on analysis and projections, the Ministry of Transport has asked the Prime Minister to allocate $137.8 million from the State budget for land clearance and resettlement.
The Ninh Binh-Thanh Hoa project is part of the North-South Expressway that will cover 654km.
Work is expected to start in 2019.