Accordingly, the repair of branch S1H of AAG will finish on January 9, one week later than initially planned, and of branch S1I January 15.
Meanwhile, the problem on the Asia Africa Europe (AAE-1) cable will be fixed from January 22 to January 27.
Repair work on branches S2 and S1 of Tata TGN-Intra Asia (IA) cable is scheduled to be completed on January 29 and February 3.
On December 22, the three cables concurrently encountered problems, causing a loss of 30 percent to the international internet transmission capacity of Vietnam.
With the above-mentioned schedule, the country’s international internet transmission capacity will be fully recovered before Tet. However, the repair plan could also be changed depending on weather conditions at sea./.
Undersea cables’ breakdown affects Internet connections in Vietnam
Internet connections in Vietnam could slow down through the upcoming New Year’s holidays after three undersea cables encountered problems.